The primary driver for the renewal is that the current play area assets are fully depreciated and have reached their end of life. The play area is 20 years old and has non-compliance issues on different pieces of equipment and the safety surfaces, in relation to the current NZ Standards for playground equipment and surfacing.
Construction began on 21 October, with completion planned before the start of the Christmas break on 25 December, weather dependent.
During this period, we recommend that people try the Burbank Crescent & Amesbury Drive play areas in Churton Park, or John Walker Park in Johnsonville.
Play Area locations
Background
Two concept designs were included in the public consultation on the renewal. Based on feedback, concept 1 was the overwhelming favourite between the two designs presented. We have then tried to accommodate additional requests where we can.
There were some requests that we were not able to accommodate, largely to do with budget constraints and the layout of the site.
For more information on the consultation, see the Churton Park play area refresh consultation page.
Contact us
If you have any questions please contact Matthew Beres, Play Spaces Specialist.
matthew.beres@wcc.govt.nz